Question 9
The October 2019 Hobbing workstation schedule shows a capacity of 400 units on Monday and 800 units on Tuesday through Saturday, with Sundays off. The Broaching workstation runs at 780 units per day, Tuesday through Saturday, with Sunday and Monday off. In a standard week, what is the total combined weekly capacity of both workstations?
Hobbing: 4,400 + Broaching: 3,900 = 8,300 units
Hobbing: 4,800 + Broaching: 3,900 = 8,700 units
Hobbing: 4,400 + Broaching: 4,680 = 9,080 units
Hobbing: 4,000 + Broaching: 3,120 = 7,120 units