Question 3: The Production rate of an assembly line is determined by …

Question 3

+1 markOne correct option

The Production rate of an assembly line is determined by its

  1. A

    Slowest station

  2. B

    Fastest station

  3. C

    Idle station

  4. D

    None of these

Show answer

Correct answer

  • A

    Slowest station

Question 3 of 15 in the IIT Madras BS Industry 4.0 (Industry 4.0) Quiz 1 paper sat on 29 Oct 2023, in the September 2023 term (IIT M DEGREE AN2 EXAM QPE2 29 Oct 2023). It carries 1 mark.

This question was also asked in

More questions from this paper

  1. Q1Match Col A with Col B for landmark outcome of industrial era
  2. Q2Identify the Industry 4.0 version of transportation.
  3. Q4Select the layout(s) which require(s) general supervision:
  4. Q5Select the appropriate layout for Quadrants A, B, D in the following figure:
  5. Q6Which of the following is an advantage of Product Layout?
  6. Q7Select the correct statements from below:
  7. Q8Identify the examples for Offshoring from the list below:
  8. Q9What is the cycle time (in seconds) at any workstations (round your answer to one decimal).
  9. Q10What is the theoretical minimum number of workstations required?
  10. Q11Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the …
  11. Q12Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the …
  12. Q13Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the …
  13. Q14Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the …
  14. Q15Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the …