Industry 4.0 Quiz 1: 29 October 2023 (September 2023 term)

The IIT Madras BS Industry 4.0 (Industry 4.0) Quiz 1 paper sat on 29 Oct 2023, in the September 2023 term: 15 questions for 20 marks in 120 minutes. Every question is below with its answer. Take it as a timed mock test to be marked, or read it through first.

Questions
15
Marks
20
Duration
120 min
MCQ
5
MSQ
4
Numerical
6

Updated

Official paper: IIT M DEGREE AN2 EXAM QPE2 29 Oct 2023 · No negative marking.

Question 1

+2 marksOne correct option

Match Col A with Col B for landmark outcome of industrial era

  1. A

    1.0:CNC, 2.0:Mass production, 3.0: Digitization, 4.0:Steam Engine

  2. B

    1.0:Steam Engine, 2.0:mass production, 3.0: digitization, 4.0:CNC

  3. C

    1.0:Mass production, 2.0:Steam Engine, 3.0: digitization, 4.0:CNC

  4. D

    1.0:Steam Engine, 2.0:mass production, 3.0: CNC, 4.0: Digitization

Show answer

Correct answer

  • D

    1.0:Steam Engine, 2.0:mass production, 3.0: CNC, 4.0: Digitization

Question 2

+1 markOne correct option

Identify the Industry 4.0 version of transportation.

  1. A

    IC engine

  2. B

    Electric car

  3. C

    Hyperloop

Show answer

Correct answer

  • C

    Hyperloop

Question 3

+1 markOne correct option

The Production rate of an assembly line is determined by its

  1. A

    Slowest station

  2. B

    Fastest station

  3. C

    Idle station

  4. D

    None of these

Show answer

Correct answer

  • A

    Slowest station

Question 4

+1.5 marksOne or more correct options

Select the layout(s) which require(s) general supervision:

Select all that apply.

  1. A

    Product layout

  2. B

    Process layout

  3. C

    Group layout

  4. D

    Fixed position layout

Show answer

Correct answers

  • A

    Product layout

  • C

    Group layout

  • D

    Fixed position layout

Question 5

+1.5 marksOne correct option

Select the appropriate layout for Quadrants A, B, D in the following figure:

  1. A

    A: Group layout, B: Product layout , D: Process layout

  2. B

    A: Process layout, B: Group layout , D: Product layout

  3. C

    A: Product layout, B: Process layout , D: Group layout

Show answer

Correct answer

  • B

    A: Process layout, B: Group layout , D: Product layout

Question 6

+1 markOne or more correct options

Which of the following is an advantage of Product Layout?

Select all that apply.

  1. A

    Small in-process inventory

  2. B

    It can accommodate high variety of products

  3. C

    High utilization of machines

  4. D

    Low investment

Show answer

Correct answer

  • A

    Small in-process inventory

Question 7

+2 marksOne or more correct options

Select the correct statements from below:

Select all that apply.

  1. A

    Optimal solution in a facility location problem using Euclidean method will result in a region

  2. B

    Optimal solution in a facility location problem using Euclidean method rarely matches the center of gravity

  3. C

    Optimal solution in a facility location problem using Euclidean method will result in a point

  4. D

    Optimal solution in a facility location problem using Euclidean method matches the center of gravity in not of the cases

Show answer

Correct answers

  • B

    Optimal solution in a facility location problem using Euclidean method rarely matches the center of gravity

  • C

    Optimal solution in a facility location problem using Euclidean method will result in a point

Question 8

+2 marksOne or more correct options

Identify the examples for Offshoring from the list below:

Select all that apply.

  1. A

    Shell, an oil company based in Netherlands, setting up a data science team in India.

  2. B

    Western Australia’s electricity network agency assigns Tata Consultancy Services at Pune, to support it with an overhaul of its legacy IT systems, aimed at delivering cheaper and more reliable power.

  3. C

    Target Corporation, a retail giant based in US, setting up Supply Chain Optimization team at Bengaluru.

  4. D

    Tata Motors assigns the manufacturing of its braking system to TACO group.

Show answer

Correct answers

  • A

    Shell, an oil company based in Netherlands, setting up a data science team in India.

  • C

    Target Corporation, a retail giant based in US, setting up Supply Chain Optimization team at Bengaluru.

Question 9

+1 markNumerical answer

A factory works for two 8-hour shifts each day and produces a total of 30,000 electric bulbs using a set of workstations. There are 8 activities required to manufacture the bulb, such that the sum of all activity times is equal to 12 seconds. Answer the given subquestions:

What is the cycle time (in seconds) at any workstations (round your answer to one decimal).

Show answer

Correct answer: 1.85 (accepted within ±0.15)

Question 10

+1 markNumerical answer

A factory works for two 8-hour shifts each day and produces a total of 30,000 electric bulbs using a set of workstations. There are 8 activities required to manufacture the bulb, such that the sum of all activity times is equal to 12 seconds. Answer the given subquestions:

What is the theoretical minimum number of workstations required?

Show answer

Correct answer: 7

Question 11

+1 markNumerical answer

Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the respective activity times in minute.

Based on the above data, answer the given subquestions.

What is the minimum cycle time of the system (in minute)?

Show answer

Correct answer: 12

Question 12

+1 markNumerical answer

Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the respective activity times in minute.

Based on the above data, answer the given subquestions.

What is the maximum cycle time of the system (in minute)?

Show answer

Correct answer: 85

Question 13

+1 markOne correct option

Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the respective activity times in minute.

Based on the above data, answer the given subquestions.

The factory works for one 8-hour shifts each day. Is it possible to achieve an output of 32 units/day,

  1. A

    Yes

  2. B

    No

Show answer

Correct answer

  • A

    Yes

Question 14

+2 marksNumerical answer

Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the respective activity times in minute.

Based on the above data, answer the given subquestions.

What is the balance delay of the following layout (round it to two decimals)
(1,2) -> (3) -> (4) -> (5) -> (6,7) -> (8,9) -> (10,11,12)

Show answer

Correct answer: 19 (accepted within ±0.5)

Question 15

+1 markNumerical answer

Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the respective activity times in minute.

Based on the above data, answer the given subquestions.

What is the efficiency of the given layout? Round off to two decimals without percentage sign

Show answer

Correct answer: 80.5 (accepted within ±0.5)