Question 14
Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the respective activity times in minute.
Based on the above data, answer the given subquestions.
What is the balance delay of the following layout (round it to two decimals)
(1,2) -> (3) -> (4) -> (5) -> (6,7) -> (8,9) -> (10,11,12)