Question 8: The Production rate of an assembly line is determined by …

Question 8

+1 markOne correct option

The Production rate of an assembly line is determined by its

  1. A

    Slowest station

  2. B

    Fastest station

  3. C

    Idle station

  4. D

    None of these

Show answer

Correct answer

  • A

    Slowest station

Question 8 of 20 in the IIT Madras BS Industry 4.0 (Industry 4.0) Quiz 1 paper sat on 26 Oct 2025, in the September 2025 term (IIT M DEGREE AN EXAM QDB2 26 Oct 2025). It carries 1 mark.

This question was also asked in

More questions from this paper

  1. Q1Match Col A with Col B for landmark outcome of industrial era :
  2. Q2Identify the Industry 4.0 version of transportation.
  3. Q3Select the layout(s) which do not require general supervision:
  4. Q4Which of the following is an advantage of Process Layout?
  5. Q5Following is the layout from an aircraft manufacturing company. Identify the layout from the figure below.
  6. Q6Select the appropriate layout for Quadrants A, B, D in the following figure:
  7. Q7Which of the following is an advantage of Product Layout?
  8. Q9Select the correct statements from below:
  9. Q10Identify the examples for Offshoring from the list below:
  10. Q11What is the cycle time (in seconds) at any workstations (round your answer to one decimal e.g. if your answer is 1.89 t…
  11. Q12What is the theoretical minimum number of workstations required?
  12. Q13Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the …
  13. Q14Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the …
  14. Q15Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the …
  15. Q16Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the …
  16. Q17Consider the following precedence diagram. It has 12 activities. The numbers in blue and withing the braces denote the …
  17. Q18There are four demand points at A(1,2), B(2,3), C(3,5), D(4,1). The respective demand at these points are 7, 1, 3, 5. S…
  18. Q19Calculate the Euclidean distance between two machines located at the coordinates A(5,10) and B(2,6) in a shop floor.\ […
  19. Q20POCOMO Mobile manufactures mobile phones of various types. Their product portfolio comprises of 15 types of headsets. T…