Question 2
Consider the Gantt chart as follows:
Select the correct observations from the given Gantt chart.
Component design starts once the user interface and database schema are completed
User interface and database design can start at the same time
Update status and reschedule task both are done concurrently
Task manager must complete before task reviewer starts