Question 19
A project manager assesses the following risks for a software project.
If the project manager prioritizes risks based on their risk scores, which of the following risks should receive the lowest priority?
R1
R2
R3
R4
A project manager assesses the following risks for a software project.
If the project manager prioritizes risks based on their risk scores, which of the following risks should receive the lowest priority?
R1
R2
R3
R4
Correct answer
R4
Question 19 of 28 in the IIT Madras BS Software Engineering (Software Engineering) End Term paper sat on 13 Sept 2026, in the May 2026 term (Software Engineering 13 Sep 26). It carries 4 marks.