Industry 4.0 Quiz 1 23 Feb 2025 — Question 7

Question 7

+2 marksOne or more correct options

Select the correct statements from below:

Select all that apply.

  1. A

    Optimal solution in a facility location problem using Euclidean method will result in a region

  2. B

    Optimal solution in a facility location problem using Euclidean method rarely matches the center of gravity

  3. C

    Optimal solution in a facility location problem using Euclidean method will result in a point

  4. D

    Optimal solution in a facility location problem using Euclidean method matches the center of gravity in not of the cases

Show answer

Correct answers

  • B

    Optimal solution in a facility location problem using Euclidean method rarely matches the center of gravity

  • C

    Optimal solution in a facility location problem using Euclidean method will result in a point

Question 7 of 15 in the IIT Madras BS Industry 4.0 (Industry 4.0) Quiz 1 paper sat on 23 Feb 2025, in the January 2025 term (IIT M DEGREE AN EXAM QDB2 23 Feb 2025). It carries 2 marks.

This question was also asked in

More questions from this paper

  1. Q1Select the appropriate layout for Quadrants A, B, D in the following figure:
  2. Q2Which of the following is an advantage of Process Layout?
  3. Q3Following is the layout from an aircraft manufacturing company. Identify the layout from the figure below.
  4. Q4Figure question
  5. Q5When will of the following scenarios, a facility layout problem is relevant?
  6. Q6Identify the examples for Offshoring from the list below:
  7. Q8There are four demand points at A(1,2), B(2,3), C(3,5), D(4,1). The respective demand at these points are 7, 1, 3, 5. S…
  8. Q9What is the cycle time (in seconds) at any workstations (round your answer to one decimal).
  9. Q10What is the theoretical minimum number of workstations required?
  10. Q11What is the minimum cycle time of the system? (in min)
  11. Q12What is the maximum cycle time of the system? (in min)
  12. Q13What is the balance delay of the following layout (round it to two decimals)\ (1,2) -> (3) -> (4) -> (5) -> (6,7) -> (8…
  13. Q14What is the efficiency of the layout, Mentioned in the previous question? (Round off to two decimals without percentage…
  14. Q15The factory works for one 8-hour shifts each day. Is it possible to achieve an output of 32 units/day.