Question 11: Consider the activity network diagram as follows: Select…

Question 11

+4 marksOne or more correct options

Consider the activity network diagram as follows:

Select the dependencies which are true from the given activity network.

Select all that apply.

  1. A

    The tasks User interface and Database schema both can be done
    simultaneously.

  2. B

    The task Search and download results can start when the task Result management is completed.

  3. C

    The task Students support system can start when the task Result management is completed.

  4. D

    The task Students record management can start only when the tasks Result management and Students' authentication both are completed.

Show answer

Correct answers

  • A

    The tasks User interface and Database schema both can be done
    simultaneously.

  • C

    The task Students support system can start when the task Result management is completed.

Question 11 of 22 in the IIT Madras BS Software Engineering (Software Engineering) Quiz 2 paper sat on 4 Aug 2024, in the May 2024 term (IIT M DEGREE AN EXAM QDB2 4 Aug 2024). It carries 4 marks.

More questions from this paper

  1. Q1An organization is developing a web service that monitors online traffic and user activity to gain valuable insights an…
  2. Q2An organization has developed a web application that enables conversion between various document formats. Before releas…
  3. Q3A software organization gathers requirements to develop an e-shopping application and is therefore planning to intervie…
  4. Q4Consider building a portal for an educational institute which has the following two requirements: Requirement 1: Studen…
  5. Q5Consider an email application with features like compose email, navigate inbox, etc. However, the application has a lim…
  6. Q6Gold plating is considered a business risk. -- What does "gold plating" mean in the given context?
  7. Q7Which of the following provides the definition of an "interface" in the context of the outcomes of software design?
  8. Q8Consider a module with a set of functions that execute in a sequence; however, they work towards entirely different pur…
  9. Q9Which of the following correctly describes the term "debugging"?
  10. Q10Which of the following is/are the advantage(s) of prototype model for software development?
  11. Q12Given that software development predominantly occurs in a distributed setting, it is essential for the developer to com…
  12. Q13Figure question
  13. Q14Figure question
  14. Q15Consider a web application that enables you to search, compare and purchase various stationary items. However, to avail…
  15. Q16Figure question
  16. Q17A developer team has used some components during the development for which they do not have access to the source code (…
  17. Q18Consider the design of an online shop that sells computers, laptops, and related accessories, along with software licen…
  18. Q19Figure question
  19. Q20A software company has to develop a mobile app that lets its users buy and sell used electronics. The requirements for …
  20. Q21A software company has to develop a mobile app that lets its users buy and sell used electronics. The requirements for …
  21. Q22Figure question