Question 10
In software project estimation, what is the primary goal of using the "Delphi Technique"?
To encourage open and collaborative communication among team members.
To provide a quick and rough estimate of project costs.
To combine estimates from multiple experts to reach a consensus estimate.
To create a detailed work breakdown structure.