Question 9
Suppose the risk assessed for budget slippage is 1.8, and the probability of budget slippage occurring during project development is 0.9. What is the impact of budget slippage on project development?
16.6
2
3
0.17
Suppose the risk assessed for budget slippage is 1.8, and the probability of budget slippage occurring during project development is 0.9. What is the impact of budget slippage on project development?
16.6
2
3
0.17
Correct answer
2
Question 9 of 24 in the IIT Madras BS Software Engineering (Software Engineering) Quiz 2 paper sat on 16 Mar 2025, in the January 2025 term (IIT M DEGREE AN EXAM QDB2 16 Mar 2025). It carries 4 marks.