Question 12
A team completes 4 story points in one sprint. This value is used to predict future progress. What is this value called?
Throughput
Capacity
Velocity
Burn rate
A team completes 4 story points in one sprint. This value is used to predict future progress. What is this value called?
Throughput
Capacity
Velocity
Burn rate
Correct answer
Velocity
Question 12 of 25 in the IIT Madras BS Software Engineering (Software Engineering) Quiz 2 paper sat on 12 Apr 2026, in the January 2026 term (Software Engineering 07 Apr 26). It carries 4 marks.