Question 18
At the end of a sprint, the team demonstrates completed features to stakeholders. This activity is called:
Sprint Planning
Sprint Review
Sprint Retrospective
Daily Scrum
At the end of a sprint, the team demonstrates completed features to stakeholders. This activity is called:
Sprint Planning
Sprint Review
Sprint Retrospective
Daily Scrum
Correct answer
Sprint Review
Question 18 of 25 in the IIT Madras BS Software Engineering (Software Engineering) End Term paper sat on 10 May 2026, in the January 2026 term (Software Engineering 06 May 26). It carries 4 marks.