Question 3
What is velocity from the agile project estimation perspective?
Number of user stories per sprint
Number of points per sprint
The time required to complete an agile project
The point assigned to each user story
What is velocity from the agile project estimation perspective?
Number of user stories per sprint
Number of points per sprint
The time required to complete an agile project
The point assigned to each user story
Correct answer
Number of points per sprint
Question 3 of 26 in the IIT Madras BS Software Engineering (Software Engineering) End Term paper sat on 1 Sept 2024, in the May 2024 term (IIT M DEGREE AN EXAM QDB3 01 Sep 2024). It carries 3 marks.