Question 14
Consider the following activities .
We can execute one activity at a time. Each activity has activity duration , which represents the time required to complete, and a deadline . Consider the initial start time to start the first selected activity. Let the lateness of a schedule be the maximum amount by which any single activity is late in that schedule. What is the minimum lateness across all possible schedules?
2
3
4
5