Question 12
Currently, a company is using a layout which consists of 10 workstations. 200 cakes are baked in a day on this layout. A typical day consists of a single shift which runs for 8 hours. The cake baking process consists of 10 activities (the information is provided in the table below). Then answer the given subquestions
Currently, a company is using a layout which consists of 10 workstations. 200 cakes are baked in a day on this layout. A typical day consists of a single shift which runs for 8 hours. The cake baking process consists of 10 activities (the information is provided in the table below). Then answer the given subquestions
Given the activity information, (theoretically) how many workstations can be reduced from the current line while achieving the maximum possible output?