Consider the following precedence diagram. It has 12 activities. The numbers in blue and within the braces denote the respective activity times in minute.

Answer the given subquestions based on the above diagram.

What is the minimum cycle time of the system? (in minutes)

Show answer

Correct answer: 12

Question 20 of 34 in the IIT Madras BS Industry 4.0 (Industry 4.0) End Term paper sat on 24 Dec 2023, in the September 2023 term (IIT M DEGREE FN EXAM FDB1 24 Dec 2023). It carries 1 mark.

More questions from this paper

  1. Q1Which of the following is not a form of internet?
  2. Q2What is First Mile in a supply chain?
  3. Q3Which of the following facility layout is best suited for manufacturing several different products of similar types usi…
  4. Q4Which type of layout is preferred for building construction?
  5. Q5Which layout is apt for low volume production of highly customized products?
  6. Q6Identify the Industry 4.0 version of transportation.
  7. Q7What are the inputs for an order-upto-level calculation?
  8. Q8Which of the following is/are considered in the Vehicle Routing Problem but not considered in TSP?
  9. Q9Which of the following supply chain costs is/are affected by distribution network structure?
  10. Q10Calculate the Metropolitan distance between two machines located at the coordinates A(5,10) and B (2,6) in a shop floor.
  11. Q11Suppose a company wants to expand its logistics network and locate a new warehouse within a network of three existing f…
  12. Q12A factory works for two 8 hour shifts each day and produces a total of 24,000 electric bulbs using a set of workstation…
  13. Q13Select the correct statements from below:
  14. Q14Which are the two primary tasks of time series forecasting?
  15. Q15Which of the following example(s) can be referred as seasonal pattern?
  16. Q16Bluescope company estimates its ordering cost at Rs 400 and carrying cost to be Rs. 2/year/unit. The estimated annual r…
  17. Q17Bluescope company estimates its ordering cost at Rs 400 and carrying cost to be Rs. 2/year/unit. The estimated annual r…
  18. Q18Bluescope company estimates its ordering cost at Rs 400 and carrying cost to be Rs. 2/year/unit. The estimated annual r…
  19. Q19Bluescope company estimates its ordering cost at Rs 400 and carrying cost to be Rs. 2/year/unit. The estimated annual r…
  20. Q21Consider the following precedence diagram. It has 12 activities. The numbers in blue and within the braces denote the r…
  21. Q22Consider the following precedence diagram. It has 12 activities. The numbers in blue and within the braces denote the r…
  22. Q23Select the correct form of internet from column B corresponding to the example in Column A.
  23. Q24Figure question
  24. Q25Which of the following is not an example of digitization?
  25. Q26What does the state variable represent?
  26. Q27What does the action set represents?
  27. Q28What is the objective function value in Stage-2?
  28. Q29What is the optimal route?
  29. Q30What is the Booking limit?
  30. Q31What is the protection level?
  31. Q32Ramu puts up a stall for Diwali Light (Diya) every year. He builds a Diya at a cost of Rs. 2 and sells for Rs. 4. Any D…
  32. Q33Ramu puts up a stall for Diwali Light (Diya) every year. He builds a Diya at a cost of Rs. 2 and sells for Rs. 4. Any D…
  33. Q34Ramu puts up a stall for Diwali Light (Diya) every year. He builds a Diya at a cost of Rs. 2 and sells for Rs. 4. Any D…