Rana Bakery, a company, uses a layout consisting of 9 workstations. Each day, 200 sandwiches are produced using this layout. A typical workday consists of a single 10-hour shift. The sandwich-making process comprises 9 activities, as detailed in the table below.
Rana Bakery, a company, uses a layout consisting of 9 workstations. Each day, 200 sandwiches are produced using this layout. A typical workday consists of a single 10-hour shift. The sandwich-making process comprises 9 activities, as detailed in the table below.
What is the current efficiency of the line where each activity is performed at a separate workstation? (Enter only the numerical value up to two decimal places without the '%' symbol. For example, if the answer is 99.756%, enter only '99.76').