Question 13
Calculate the given subquestion for Gear Broaching Process for Week 1
| Parameters | Week 1 |
|---|---|
| No. of Shifts/ Day | 3 |
| No. of Working Days in the Week | 6 |
| No. of Hours/Shift | 8 |
| Number of Shifts lost due to maintenance | 3 |
| Designed Speed of Broaching Process (per hour) | 60 |
| Total Product Output | 6243 |
| Scrap (S) | 501 |
Performance ________% (upto one decimal point)