Business Data Management · End Term · 30 Apr 2023 · January 2023 term · Set QPD1-S1

Question 15: Calculate the given subquestions for Gear Hobbing Proces…

Question 15

+2 marksNumerical answer

Calculate the given subquestions for Gear Hobbing Process for Week 1

ParametersWeek 1
No. of Shifts/ Day (No Holiday on any day of the week)3
No. of Hours/Shift8
Number of Shifts lost due to maintenance6
Designed Speed of Hobbing Process (per hour)60
Total Product Output6200
Scrap (S)422

Quality ________%

Show answer

Correct answer: 93.25 (accepted within ±0.75)

Question 15 of 18 in the IIT Madras BS Business Data Management (BDM) End Term paper sat on 30 Apr 2023, in the January 2023 term (IIT M DIPLOMA ET1 EXAM QPD1 S2 30 Apr 2023). It carries 2 marks.

More questions from this paper

  1. Q1When does marginal utility become negative?
  2. Q2The current ratio is a measure of:
  3. Q3A Company has current assets of \500,000 and current liabilities of \250,000. What is the current ratio of the company?
  4. Q4Match the following | 1 | Pricing Decisions | A | Process that integrates various business processes, functions, and de…
  5. Q5What do regional tables signify?
  6. Q6Which of the SKU should be placed closer to the processing center?
  7. Q7Match the following | 1 | Ashmit who has not got his KYC done, applied for a credit of 120 rupees but got rejected. | A…
  8. Q8Suppose you have an Excel cell containing the following text string: "03/12/2022 14:36:00". Which of the following form…
  9. Q9If the price of a product increases by 10% and the quantity demanded decreases by 20%, what is the price elasticity of …
  10. Q10Consider the dataset. Rank the candidates, and choose the option correctly. Here appraisal score, duration in the curre…
  11. Q11Give the preference order in which the following people are most likely to get their credit request approved | Customer…
  12. Q12The following table provides the number of credit applications approved or declined in 4 months in 2021 Which Month has…
  13. Q13Calculate the given subquestions for Gear Hobbing Process for Week 1 | Parameters | Week 1 | |---|---| | No. of Shifts/…
  14. Q14Calculate the given subquestions for Gear Hobbing Process for Week 1 | Parameters | Week 1 | |---|---| | No. of Shifts/…
  15. Q16Calculate the given subquestions for Gear Hobbing Process for Week 1 | Parameters | Week 1 | |---|---| | No. of Shifts/…
  16. Q17Total Output of Gear Casts after Broaching: 2300\ Cost of Broaching: INR 27 per Gear cast, Raw Material Cost: INR 43 pe…
  17. Q18Total Output of Gear Casts after Broaching: 2300\ Cost of Broaching: INR 27 per Gear cast, Raw Material Cost: INR 43 pe…